2019 Build Schedule

Hernando DeSoto Habitat for Humanity

Tentative 2019 Fall Build Schedule
For New Construction Home
2694 Ginn Street, Hernando, MS 38632
Please Note:  All Workdays Start at 8:00 A.M.

Numbers in Parentheses—Approximate # of Volunteers Needed

December 2019

7—Saturday, Workday #1—Framing (25)
14—Saturday, Workday #2—Framing (25)
21—Saturday, Workday #3—Roofing, Windows, Exterior Doors (25)
28—Saturday, No Work Scheduled—Rough-Ins by Subs

January 2020

4—Saturday, No Work Scheduled—Rough-Ins by Subs
11—Saturday, Workday #4—Sand & Paint Interior Walls (15)
18—Saturday, Workday #5—Install Interior Doors, Trim, Paint (15)
20—Monday, Holiday
25—Saturday, Workday #6—Interior Finish Work (15)

February 2020

1—Saturday, Workday #7—Interior Finish Work (15)
8—Saturday, Workday #8—Cabinets, Trim, Yard (15)
15—Saturday, Workday #9—Grounds—Landscaping & Sod Installation (25)
17—Monday, Holiday
22—Saturday, Workday #10— Bath Hardware, Paint (10)
29—Saturday, Workday #11— Final Touch-Up, Cleaning, Floor Finish (10)

March 2020

1—Sunday, Planned Home Dedication Service Date—2:00 P.M.